UFGS Changes and Revisions  Subscribe to UFGS Changes and Revisions

Related Materials: Policy on UFGS Changes and Revisions

Below is a listing of the Revisions and Changes made to UFGS Sections for each quarterly release.

To view a list for a specific UFGS Release, select the UFGS release date from the 'Release' drop-down and click 'Apply'.

To view a list of all the revisions and changes made to a specific UFGS Section, select 'Any' from the "Release' drop down, type the Section number into the Search bar and select the Section to view, then click 'Apply'.

After clicking 'Apply', you can PRINT REPORT, which will include the nature of the change/revision.

To view the complete detailed history of all the revisions and changes made to a UFGS Section, click on the Section title.

KEY PREPARING ACTIVITY (PA) A Army N Navy F Air Force S NASA
ACTION N New R Revision C Change D Deletion
Release PA UFGS Section Actionsort ascending Change # Nature of Change or Revision
Aug-2020 A UFGS 35 20 15 FRP Composites for Low-Head Water Control Structures C 1 Deleted third paragraph of subpart 1.8.3 in response to CCR 7032.
Aug-2020 N UFGS 01 14 00 Work Restrictions C 10 Incorporate EURAFCENT requirements from, and supersede UFGS 00 74 00 SUPPLEMENTARY CONDITIONS FOR PROJECTS IN MEDITERRANEAN AREA. Also, incorporate the following CCRs: CCR 8681, revised requirements to ensure adherence to all appropriate PPE in paragraphs "Activity Regulations" (1.5.1) and "Shipyard Regulations" (1.5.3); CCR 8683, updated Specifier Note and paragraph "Working Hours" (1.5.5) to reflect the work schedules for various regions.
Aug-2020 N UFGS 01 20 00.00 20 Price and Payment Procedures C 3 In response to CCR 8819, changes to submittal requirements for NAVFAC PAC to mitigate schedule impacts: added Note under Submittal Article SD-01 and in paragraph "Data Required" (1.3.1)
Aug-2020 N UFGS 01 30 00 Administrative Requirements C 4 In response to CCRS 8820 and 9015, changes to submittal requirements for NAVFAC PAC to mitigate schedule impacts: added Note under Submittal Article SD-01, updated paragraph "Formal Partnering" (1.12.1), and added paragraph "MOBILIZATION" (1.14).
Aug-2020 N UFGS 01 31 23.13 20 Electronic Construction and Facility Support Contract Management System (eCMS) C 5 In response to CCR 8821, changes to submittal requirements for NAVFAC PAC to mitigate schedule impacts: added Note under Submittal Article SD-01
Aug-2020 N UFGS 01 32 16.00 20 Small Project Construction Progress Schedules C 1 In response to the following CCRs: CCR 8738, clarified adverse weather requirements and schedule modifications required due to non-work days in paragraph "Anticipated Weather Lost Work Days" (1.3.1.2); CCRs 8822 and 9013, changes to submittal requirements for NAVFAC PAC to mitigate schedule impacts: added Note under Submittal Article SD-01 and updated paragraph "PRE-CONSTRUCTION SCHEDULE REQUIREMENT" (1.2).
Aug-2020 N UFGS 01 32 17.00 20 Cost-Loaded Network Analysis Schedules (NAS) C 3 In response to the following CCRs: CCR 8739, paragraph "Construction Activities" (1.10.2.5.6) has been updated to clarify federal holidays; CCR 8891, clarified schedule deliverables due from the contractor and added checklists for the KTR as attachments (found under Related Materials) ; CCR 8971, revised Note in Submittals Article regarding Design-Build Requirements; and CCR 8823, changes to submittal requirements for NAVFAC PAC to mitigate schedule impacts: updated paragraphs "Project Baseline Schedule" (1.2.2), Submittal Article SD-01, and "DESIGNATED PROJECT SCHEDULER" (1.9).
Aug-2020 N UFGS 01 35 26 Governmental Safety Requirements C 10 In response to CCR 8826, changes to submittal requirements for NAVFAC PAC to mitigate schedule impacts: added Note under Submittal Article SD-01 and updated paragraph "ACCIDENT PREVENTION PLAN (APP)" (1.8).
Aug-2020 N UFGS 01 45 00.00 20 Quality Control C 7 In response to the following CCRs: CCR 8960, the Note pertaining to paragraph "Registered Fire Protection Engineer" (1.5.8) has been revised for clarity; CCR 8961, paragraph "QC Administrative Assistant" (1.5.10) has been removed to align with the other QC sections; CCR 8827, changes to submittal requirements for NAVFAC PAC to mitigate schedule impacts: revised Submittal Article SD-01 and paragraph "CONSTRUCTION INDOOR AIR QUALITY (IAQ) MANAGEMENT PLAN" (1.17).
Aug-2020 N UFGS 01 45 00.10 20 Quality Control for Minor Construction C 2 In response to CCR 8828, changes to submittal requirements for NAVFAC PAC to mitigate schedule impacts: added Note under Submittal Article SD-01 and Note and to paragraph "QC PLAN" (1.6).
Aug-2020 N UFGS 01 57 19 Temporary Environmental Controls C 4 In response to CCR 8832, changes to submittal requirements for NAVFAC PAC to mitigate schedule impacts: added Note under Submittal Article SD-01 and paragraph "ENVIRONMENTAL PROTECTION PLAN" (1.7); under paragraphs "Stormwater Pollution Prevention Plan" (3.2.1.1) and "Stormwater Notice of Intent for Construction Activities" (3.2.1.2) added note and text.
Aug-2020 N UFGS 01 57 19.01 20 Supplemental Temporary Environmental Controls C 3 Additional change made regarding CCR 8507, the section has been updated to clarify requirements for surplus soil disposal at Camp Lejenue (1.4.6.1.2). In response to CCR 8833, changes to submittal requirements for NAVFAC PAC to mitigate schedule impacts: added Note under SD-01 and in paragraph "Notice of Construction (NOC) and Notice of Completion" (1.5.3.6).
Aug-2020 N UFGS 01 58 00 Project Identification C 1 In response to CCR 8950, revised Specifier Note in paragraph Quality Control (1.3) for additional guidance.
Aug-2020 N UFGS 07 21 13 Board and Block Insulation C 2 In response to CCR 8689, updated phrasing used in SPECIAL WARRANTIES (1.8) for the start of the warranty period to include "or Substantial Completion".
Aug-2020 N UFGS 07 27 19.01 Self-Adhering Air Barriers C 2 In response to CCR 8741, "Qualifications of Manufacturer" and "Qualification of Installer" were removed from SD-07 in the Submittal Article since both are already listed under SD-01.
Aug-2020 N UFGS 07 27 26 Fluid-Applied Membrane Barriers C 2 In response to the following CCRs: 8742, "Qualifications of Manufacturer" and "Qualification of Installer" were removed from SD-07 in the Submittal Article since both are already listed under SD-01; and 8779, added Specifier Note and dry film thickness requirements to paragraph "Installation of Fluid-Applied Membrane Air Barrier" (3.3.3) .
Aug-2020 N UFGS 07 27 36 Spray Foam Air Barriers C 2 In response to CCR 8743, "Qualifications of Manufacturer" and "Qualification of Installer" were removed from SD-07 in the Submittal Article since both are already listed under SD-01.
Aug-2020 N UFGS 07 41 13 Metal Roof Panels C 3 In response to CCR 8778, updated supporting steel tolerances to reflect industry standards in paragraph "Erection Tolerances" (3.8.1).
Aug-2020 N UFGS 07 42 63 Fabricated Wall Panel Assemblies C 4 In response to CCR 8748, "Qualifications of Manufacturer" and "Qualification of Installer" were removed from SD-07 in the Submittal Article since both are already listed under SD-01.
Aug-2020 N UFGS 08 71 00 Door Hardware C 3 In response to CCR 4895, the Specifier Note in "Locks and Latches" (2.3.5) has been revised to reflect the latest door locking system specified in the Unaccompanied Housing FC.
Aug-2020 N UFGS 09 67 23.15 Fuel Resistive Resinous Flooring, 3-Coat System C 2 In response to CCR 6045, replaced "Vulkem 245" with "Stoneflex MP7" in Table II for Vendor Stonhard's sealant.
Aug-2020 N UFGS 09 90 00 Paints and Coatings C 5 In response to the following CCRs: CCR 3281, corrected metric equivalent measurements in "Existing Surfaces with a Bituminous or Mastic-Type Coating" (3.5.6), "Concrete and Masonry" (3.6.1), and "New[, Existing Uncoated,][ and ][Existing Coated] Plywood and Wood Surfaces, Except Floors" (3.7.1); CCR 4282, added the options of corrosive environments to "Exterior Paint Tables" (3.15.1), EXTERIOR GALVANIZED SURFACES, "G" and "H"; CCR 6392, removed references to SCS Global; CCR 6869, removed "MPI 7" from References and replaced "MPI 7" with "MPI 6" in "Exterior Paint Tables" (3.15.1), Division 6 "A"; and CCR 8722, capitalized "Contractor" throughout.
Aug-2020 N UFGS 10 22 26.13 Accordion Folding Partitions C 2 In response to CCR 8746, "Statement of Code Compliance" and "Statement of Standards Conformity" were removed from SD-07 in the Submittal Article since both are already listed under SD-01.
Aug-2020 N UFGS 10 22 26.23 Coiling Partitions C 2 In response to CCR 8747, "Statement of Code Compliance" and "Statement of Standards Conformity" were removed from SD-07 in the Submittal Article since both are already listed under SD-01.
Nov-2020 A UFGS 23 09 13 Instrumentation and Control Devices for HVAC C 1 Updated ADA sensor height requirement in subpart 3.1.7.1 in response to CCR 7477.
Nov-2020 A UFGS 41 24 26 Hydraulic Power Systems C 1 Deleted all references to SAE J1165 and replaced with ISO 4406 in response to CCR 1788.
Nov-2020 A UFGS 33 56 10 Factory-Fabricated Fuel Storage Tanks C 1 Updated subpart 2.4.1 in response to CCR 7770. Updated note in subpart 2.5. Added subparts 2.6.1.1 and 2.6.2.1. Updated subpart 2.14.1 in response to CCR 9187.
Nov-2020 A UFGS 33 56 19 Fuel Impermeable Liner System C 1 Updated notes in subparts 2.1.3, 2.2.7, 3.5.1 and 3.7 in response to CCR 4564.
Nov-2020 N UFGS 01 14 00 Work Restrictions C 11 Updated Additional Personnel Requirements (1.5.1.2) and subparagraph to clarify work restrictions for secure facilities. Incorporated the following CCRs: CCR 9027, revised General Note in relation to tailoring options included in the section; CCR 9028, corrected tailoring in Part 1; and CCR 9029, corrected subpart hierarchy by moving "Unarmed Escort Services" paragraph into "CONTRACTED SERVICES FOR NBK BANGOR, SILVERDALE, WA. (1.16).
Nov-2020 N UFGS 01 78 23 Operation and Maintenance Data C 1 In opening note, incorporated Navy thresholds, from cancelled Navy ECB 2014-01, that require use of UFGS 01 78 24.00 20 FACILITY eOMSI
Nov-2020 N UFGS 01 78 24.00 20 Facility Data Workbook (FDW) C 2 In opening Note, incorporated Navy thresholds, from cancelled Navy ECB 2014-01, that require use of UFGS 01 78 24.00 20, and updated Facility Data Workbook.
Nov-2020 N UFGS 01 58 00 Project Identification C 2 [Update 3/18/21: per CCR# 9845, reference to ARRA has been removed from the sign details in all Related Materials.] Updated both the Specifier Note under PROJECT IDENTIFICATION SIGN (1.4) and the Related Materials (PDF/ZIP attachments)
Nov-2020 N UFGS 33 01 50.55 Cleaning of Petroleum Storage Tanks C 1 (UFGS-33 01 50.60) In response to CCR 7720, paragraph "TANK CLEANING" (3.7) has been updated.
Nov-2020 N UFGS 33 52 10 Fuel Systems Piping (Service Station) C 1 Updated Reference Article and paragraphs "Contractor Qualifications" (1.4.1), "Flange Gaskets, Non-Electrically Isolating" (2.2.3), "Insulating Flange Kits, (Electrically Isolating)" (2.3.2), and "Swing Type Check Valves" (2.6.3) to clarify and incorporate CCRs.
Nov-2020 N UFGS 33 52 40 Fuel Systems Piping (Non-Hydrant) C 2 Updated Reference Article, Submittals, and paragraphs "Contractor Qualifications" (1.5.1), "Insulating Flange Kits, (Electrically Isolating)" (2.2.8), "Flange Gaskets, Non-Electrically Isolating" (2.2.10), and "Flange Gaskets, Metallic" (2.2.11) to clarify and incorporate CCRs.
Nov-2020 N UFGS 33 56 21.17 Single Wall Aboveground Fixed Roof Steel POL Storage Tank C 1 Updated Reference Article and paragraphs "Weld Inspector Certification" (1.9.4), "Qualifications of API Std 653 Inspector" (1.9.7), "Mechanical Tape Level Gauge" (2.13.5) to clarify and incorporate CCRs.
Nov-2020 N UFGS 33 57 55 Fuel Systems Components (Non-Hydrant) C 1 Updated paragraph "Filters" (2.29.1.3).
Feb-2021 A UFGS 01 33 23.33 Aviation Fuel System Specific Submittal Requirements C 1 Deleted redundant drawing sizes from paragraph 1.1.1 in response to CCR 8754 and updated paragraph 2.1.1 in response to CCR 8756.
Feb-2021 A UFGS 01 78 23.33 Operation and Maintenance Manuals for Aviation Fuel Systems C 1 Deleted editing note in paragraph 2.1.2, corrected formatting issues in paragraph 2.2, and updated editing note in paragraph 3.3.6 in response to CCR 8929.
Feb-2021 A UFGS 02 61 13 Excavation and Handling of Contaminated Material C 1 Deleted and updated references in response to CCRs 2245 and 4992. Updated submittals in response to CCR 6032.
Feb-2021 A UFGS 07 54 19 Polyvinyl Chloride Roofing C 3 Updated NRCA reference in response to CCR 9568.
Feb-2021 A UFGS 21 13 25 High-Expansion Foam System, Fire Protection C 1 Updated Flanges and Gaskets paragraph in response to CCR 7781. Corrected formatting issues in response to CCR 8444. Updated paragraph 2.3.9 in response to CCR 9292.
Feb-2021 A UFGS 23 81 00 Decentralized Unitary HVAC Equipment C 1 Deleted contents of paragraph 2.3.4 and added note.
Feb-2021 A UFGS 31 00 00 Earthwork C 2 Updated paragraph 1.5.4 in response to CCR 5210. Updated reference in response to CCR 7275. Updated paragraphs in Part 3 in response to CCRs 9380, 9381, 9382 and 9384.
Feb-2021 A UFGS 33 52 43.13 Aviation Fuel Piping C 1 Updated reference publication in paragraph 2.1.6 in response to CCR 8022. Deleted redundant submittal items in response to CCR 8765. Corrected misspelled words in response to CCR 9188. Updated paragraph Contractor Qualifications to align with UFGS 33 52 40 and UFGS 33 52 10 in response to CCR 8536.
Feb-2021 A UFGS 33 52 43.14 Aviation Fuel Control Valves C 1 Updated valve body material. Corrected terminology in paragraph 1.5 in response to CCR 9173. Clarified paragraph Bodies, Bonnets, and Covers in response to CCR 9174. Updated sentence in paragraph 2.2.1.6 in response to CCR 3432.
Feb-2021 A UFGS 33 52 43.23 Aviation Fuel Pumps C 1 Updated pump casing material.
Feb-2021 N UFGS 01 20 00 Price and Payment Procedures C 1 In response to CCR 9618, reference to FAR 32.503-6 has been replaced with "FAR 32.103 Progress payments under construction contracts" in paragraph (1.7.1) "Obligation of Government Payments" .
Feb-2021 N UFGS 01 31 23.13 20 Electronic Construction and Facility Support Contract Management System (eCMS) C 6 In response to CCRs 9429 and 9621, removed reference to DoD Manual 5200.01-V4 and all FOUO designations; replaced "FOUO - For Official Use Only" with "CUI Controlled Unclassified Information" throughout; and changed CLASS heading in Table 1 to "DESIG" (designation).
Feb-2021 N UFGS 01 45 00.00 20 Quality Control C 8 In response to the following CCRs: 8956 - add reference to UFGS Section 01 32 16.00 20; and 9339 - coordinate commissioning and sustainability with UFGS Sections 01 91 00.15 20 and UFGS 01 33 29.
Feb-2021 N UFGS 01 45 00.10 20 Quality Control for Minor Construction C 3 In response to CCR 8942, "KO" has been replaced with "Contracting Officer" throughout, "Pre-Construction Conference" and "Pre-Construction Meeting" have been tailored for Army and Navy respectively, and various clerical tagging corrections have been made.
Feb-2021 N UFGS 03 30 00 Cast-In-Place Concrete C 1 In response to CCR 6876, the mark for ASTM A615/A615M reinforcing bars was changed from "A" to "S" in paragraph (2.6.1) Reinforcing Bars, list item "b".
Feb-2021 N UFGS 03 45 00 Precast Architectural Concrete C 1 In response to CCR 9837, reference to A, B and C grades were removed from the paragraph "Grout" (2.2.13).
Feb-2021 N UFGS 07 41 13 Metal Roof Panels C 4 In response to CCR 9492, updated paragraph (3.13) WARRANTY by removing "USACE" from the title and requirements for future contracts and arbitration.
Feb-2021 N UFGS 13 34 19 Metal Building Systems C 1 In response to CCR 9491, updated paragraph (3.14) WARRANTY by removing Army tailoring and Specifier Note as well as requirements for future contracts and arbitration.
Feb-2021 N UFGS 41 22 13.14 Bridge Cranes, Overhead Electric, Top Running C 1 Incorporation of cyber security requirements, clarification of testing requirements, and formatting.
Feb-2021 N UFGS 41 22 13.15 Bridge Cranes, Overhead Electric, Under Running Trolley C 1 Incorporation of cyber security requirements, clarification of testing requirements, and formatting.
Feb-2021 S UFGS 08 34 73 Sound Control Door Assemblies C 1 Added STC rating to Para 1.3.1.4 - CCR# 8318
Feb-2021 S UFGS 01 33 00 Submittal Procedures C 4 Incorporation of the following CCRs: Incorporated PPI Information CCR# 7812 - Changed Title to Certification of Submittal in 1.17 CCR# 7894 - Updated paragraph 1.6.1 for non-Army projects CCR# 8991 - Added 23 09 00 to paragraph 1.5.2 CCR# 9026 - Deleted the 2nd sentence in par 1.10.2. Added “For variations that include design changes or some material or product substitutions, the Government may require an evaluation and analysis by a licensed professional engineer hired by the contractor. in para 1.10.1 CCR# 9065 - Deleted Tailoring Notes for 1.4.2.1, 1.4.2.2, 1.4.2.3 and 1.4.2.4. Added note to 1.4.2 CCR# 9073 - Added Section 01 91 00.15 20: Commissioning Plan, Certificate of Readiness, and Commissioning Report" to paragraph 1.5.2 CCR# 9326
May-2021 A UFGS 04 01 20.75 Masonry Strengthening Using Surface Applied FRP Composites C 2 Updated subparts 3.4.3.2 and 3.4.3.3 in response to CCR 4378.
May-2021 A UFGS 06 17 19 Cross-Laminated Timber C 2 Deleted 2nd note paragraph in subpart 2.2.3 in response to CCR 8979.
May-2021 A UFGS 23 09 00 Instrumentation and Control for HVAC C 3 This change aligns PVT requirements with Navy testing processes and eliminates an extraneous tailoring option. Deleted subpart 1.8.11 and corresponding submittal item in response to CCR 9532. Updated subpart 3.10 in response to CCR 9365.
May-2021 A UFGS 23 09 13 Instrumentation and Control Devices for HVAC C 2 Updated subpart 2.7.3.4.4 in response to CCR 7146.
May-2021 A UFGS 25 10 10 Utility Monitoring and Control System (UMCS) Front End and Integration C 1 Updated cybersecurity requirements in response to CCR 9323. Deleted subpart 3.3.2 and corresponding submittal item in response to CCR 9748.
May-2021 A UFGS 32 13 15.20 Concrete Pavement for Fuel Storage Containment Dikes C 1 Added impermeable liner system requirements in response to CCR 7040.
May-2021 N UFGS 26 27 14.00 20 Electricity Metering C 1 In response to the following: CCR 937, IEC 60687 has been removed from the Reference Article and the section text; CCR 4620, the accuracy class in potential and current transformers was changed to "0.15" in paragraphs Potential Transformer Requirements (2.1.2) item f. and Current Transformer Requirements (2.1.3) item b.; and CCR 5117, reference to a 'Voltage Requirements' paragraph was removed from paragraph (2.1.5) Disconnect Method, item c.
May-2021 N UFGS 01 11 00 Summary of Work C 1 In response to CCR 8732, unnecessary brackets were removed from the last sentence in the 2nd paragraph under (1.8) LOCATION OF UNDERGROUND UTILITIES retaining the sentence as a standard requirement.
May-2021 N UFGS 03 45 00 Precast Architectural Concrete C 1 In response to CCR 9739, "High-Density Plastic" has been added as the title for paragraph 2.7.6
May-2021 N UFGS 01 14 00 Work Restrictions C 12 In response to CCR 9908, paragraph Shipyard Area Work Clearance Request (1.5.10) has been tailored for Navy.
May-2021 N UFGS 01 91 00.15 20 Total Building Commissioning C 1 Changes made to align with NAVFAC policy, and corrections of errors and omissions.
May-2021 N UFGS 23 08 00.00 20 Commissioning of Mechanical[ and Plumbing] Systems C 1 Changes made to align with NAVFAC policy, and corrections of errors and omissions.
May-2021 N UFGS 26 51 00 Interior Lighting C 1 Changes made to address various CCRs: added new paragraph (1.5.8) "Photometric Plan"; updated Specifier Note in LED Light Sources (2.3.1); updated (2.6.1.1) Exit Signs with Battery Backup and (2.6.6) Central Emergency Lighting System.
May-2021 N UFGS 03 30 00 Cast-In-Place Concrete C 2 In response to the following: CCR 7515, updated ACI 302.1R table references in paragraph (3.10.2) "Flat Floor Finishes"; CCR 7801, revised Specifier Note and list item a. in subparagraph (2.3.1.1) "Portland Cement"; CCR 8263, changed center table heading to "12 months" in subparagraph (2.5.2.4) "Sulfate Resistance" list item c.; CCR 8321, updated list item b. in subparagraph (2.3.1.3) "Fly Ash" and revised subparagraph (2.3.1.4) "Slag Cement"; CCR 8333, updated bar Grades in paragraph (2.6.1) "Reinforcing Bars" list item b. and (2.6.1.2) "Epoxy-Coated Reinforcing Bars" list item a.; CCR 8571, deleted paragraph "Perimeter Insulation" (2.2.6); CCRs 8085 and 8572 added the option “IL portland limestone cement” to subparagraph (2.3.1.2) "Blended Cements" in the Specifier Note and list item a.; CCRs 9127 and 9142, updated list item b. in paragraph (3.5.2) "Vapor Retarder [and Vapor Barrier]", replaced "air temperature" with "concrete temperature" in paragraph (3.6.2) "Mixing" list items b. and c., also added manufacturer's recommended dosage in item d., updated article (3.7) “Placing Concrete” and paragraph (3.10.1) “Finish”, and added new subparagraphs (3.14.1.1) “Fine Aggregate” and (3.14.1.2) “Course Aggregate” under (3.14.1) “Aggregate Testing”.
May-2021 N UFGS 22 00 00 Plumbing, General Purpose C 4 Added "Army" projects to the Specifier Notes under (2.1.1) Pipe Joint Materials, list item t., (3.1.3.6) Copper Tube and Pipe, list item d, and (3.12) TABLE II; added Air Force tailoring to paragraph (2.4.6) No-Water Urinals; NOTES indicating tailoring options added throughout this section.
May-2021 N UFGS 26 20 00 Interior Distribution System C 2 Incorporated CCR changes throughout this section.
May-2021 N UFGS 05 12 00 Structural Steel C 2 In response to CCR 9371, the material strength in paragraph Structural Steel Tubing (2.2.2) was updated to "Grade [C]"
May-2021 N UFGS 26 29 23 Adjustable Speed Drive (ASD) Systems Under 600 Volts C 1 Changes made to address various CCRs: added "IEC 61000-3-12" to References and paragraph Power Line Surge Protection (1.3.2.1); replaced reference UL 508C with "UL 61800-5-1"; ASD was changed to "110" percent in list item d. and "IEC" was added to list item r. in article (2.1) ADJUSTABLE SPEED DRIVES ; and article (2.2) ENCLOSURES was updated.
May-2021 N UFGS 01 57 19.01 20 Supplemental Temporary Environmental Controls C 4 In response to CCR 9422, subparagraph (1.4.6.1.1) Removal of Waste from Camp Lejeune has been updated to reflect the landfill waste policy at Camp Lejeune.
Aug-2021 A UFGS 01 50 00 Temporary Construction Facilities and Controls C 1 Added Note to Submittal Article with instructions for Navy Design-Build projects.
Aug-2021 A UFGS 01 74 19 Construction Waste Management and Disposal C 2 Added Note to Submittal Article with instructions for Navy Design-Build projects. Incorporated CCRs that support certain Navy Facilities Engineering Commands.
Aug-2021 A UFGS 01 78 00 Closeout Submittals C 1 Added Note to Submittal Article with instructions for Navy Design-Build projects. Deleted note and bracketed selections for Army only in response to CCR 8454.
Aug-2021 A UFGS 26 36 23 Automatic Transfer Switches and By-Pass/Isolation Switch C 1 Incorporated CCRs and corrected formatting errors.
Aug-2021 N UFGS 01 11 00 Summary of Work C 2 In response to CCR 9971, added note to Submittal Article for NAVFAC PAC requirement to remove Government approval of salvage plan, and modified corresponding paragraph in text.
Aug-2021 N UFGS 01 14 00 Work Restrictions C 13 In response to the following CCRs: 9044, added Note to Submittal Article with instructions for Navy Design-Build projects; 9826, updated last sentence in Activity Regulations paragraph (1.5.1) to clarify identifying Contractor equipment; 3976, replaced "must" with "will" or "may" throughout Part 1 as appropriate.
Aug-2021 N UFGS 01 20 00 Price and Payment Procedures C 2 In response to CCR 9972, included timeline requirements for both Schedule of Prices and Earned Value Report and corrected typo in Note in Data Required paragraph.
Aug-2021 N UFGS 01 30 00 Administrative Requirements C 1 In response to CCR 10208, updated requirements for NAVFAC PAC DB and DBB in Partnering and Mobilization paragraphs.
Aug-2021 N UFGS 01 35 26 Governmental Safety Requirements C 1 In response to CCR 9981, updated Note in APP-Construction paragraph to clarify instructions for NAVFAC PAC DB and DBB project options.
Aug-2021 N UFGS 01 57 19 Temporary Environmental Controls C 5 Added Note to Submittal Article with instructions for Navy Design-Build projects. In response to CCR 10213, updated requirements for NAVFAC PAC DB and DBB in Environmental Protection Plan paragraph.
Aug-2021 N UFGS 01 57 19.01 20 Supplemental Temporary Environmental Controls C 5 Added Note to Submittal Article with instructions for Navy Design-Build projects.
Aug-2021 N UFGS 01 78 23 Operation and Maintenance Data C 2 Added "Marine Corps Installations" to General Note.
Aug-2021 N UFGS 01 78 24.00 20 Facility Data Workbook (FDW) C 3 In response to CCR 8939, added bracketed option for section UFGS 01 32 16.00 20 in Pre-Construction/Post-Award Kickoff Meeting paragraph. Added "Marine Corps Installations" to General Note and updated Notes for the Facility Data Workbook; modified Notes and paragraphs to have either brackets or tailoring, not both.
Aug-2021 N UFGS 26 08 00 Apparatus Inspection and Testing C 2 Incorporated optional paragraphs in PART 3 regarding UFGS Sections 26 35 43 400-HERTZ (HZ) SOLID STATE FREQUENCY CONVERTER and 26 35 44 270 VDC SOLID STATE CONVERTER.
Aug-2021 N UFGS 32 92 19 Seeding C 1 In response to CCR 10412, "Division 2" has been replaced with "Division 31" in TOPSOIL paragraph Note to conform with CSI MasterFormat.
Aug-2021 N UFGS 32 92 23 Sodding C 1 In response to CCR 10413, "Division 2" has been replaced with "Division 31" in TOPSOIL paragraph Note to conform with CSI MasterFormat.
Aug-2021 N UFGS 32 92 26 Sprigging C 1 In response to CCR 10414, "Division 2" has been replaced with "Division 31" in TOPSOIL paragraph Note to conform with CSI MasterFormat.
Aug-2021 N UFGS 32 93 00 Exterior Plants C 1 In response to CCR 10415, "Division 2" has been replaced with "Division 31" in TOPSOIL paragraph Note to conform with CSI MasterFormat.
Aug-2021 N UFGS 32 96 00 Transplanting Exterior Plants C 1 In response to CCR 10416, "Division 2" has been replaced with "Division 31" in TOPSOIL paragraph Note to conform with CSI MasterFormat.
Nov-2021 A UFGS 01 45 00.00 10 Quality Control C 2 Incorporated CCRs 8607, 10228, 10948, and 11035.
Nov-2021 A UFGS 01 78 24.00 10 Facility Data Requirements C 1 Incorporated CCR 10987 and corrected formatting issues.
Nov-2021 A UFGS 01 74 19 Construction Waste Management and Disposal C 3 Required to align with NAVFAC regional fidelity, and to fix administrative issues, per two CCRs.