UFGS Changes and Revisions  Subscribe to UFGS Changes and Revisions

Related Materials: Policy on UFGS Changes and Revisions

Below is a listing of the Revisions and Changes made to UFGS Sections for each quarterly release.

To view a list for a specific UFGS Release, select the UFGS release date from the 'Release' drop-down and click 'Apply'.

To view a list of all the revisions and changes made to a specific UFGS Section, select 'Any' from the "Release' drop down, type the Section number into the Search bar and select the Section to view, then click 'Apply'.

After clicking 'Apply', you can PRINT REPORT, which will include the nature of the change/revision.

To view the complete detailed history of all the revisions and changes made to a UFGS Section, click on the Section title.

KEY PREPARING ACTIVITY (PA) A Army N Navy F Air Force S NASA
ACTION N New R Revision C Change D Deletion
Release PAsort descending UFGS Section Action Change # Nature of Change or Revision
Aug-2021 N UFGS 01 57 19.01 20 Supplemental Temporary Environmental Controls C 5 Added Note to Submittal Article with instructions for Navy Design-Build projects.
Aug-2021 N UFGS 01 78 23 Operation and Maintenance Data C 2 Added "Marine Corps Installations" to General Note.
Aug-2021 N UFGS 01 78 24.00 20 Facility Data Workbook (FDW) C 3 In response to CCR 8939, added bracketed option for section UFGS 01 32 16.00 20 in Pre-Construction/Post-Award Kickoff Meeting paragraph. Added "Marine Corps Installations" to General Note and updated Notes for the Facility Data Workbook; modified Notes and paragraphs to have either brackets or tailoring, not both.
Aug-2021 N UFGS 26 08 00 Apparatus Inspection and Testing C 2 Incorporated optional paragraphs in PART 3 regarding UFGS Sections 26 35 43 400-HERTZ (HZ) SOLID STATE FREQUENCY CONVERTER and 26 35 44 270 VDC SOLID STATE CONVERTER.
Aug-2021 N UFGS 32 92 19 Seeding C 1 In response to CCR 10412, "Division 2" has been replaced with "Division 31" in TOPSOIL paragraph Note to conform with CSI MasterFormat.
Aug-2021 N UFGS 32 92 23 Sodding C 1 In response to CCR 10413, "Division 2" has been replaced with "Division 31" in TOPSOIL paragraph Note to conform with CSI MasterFormat.
Aug-2021 N UFGS 32 92 26 Sprigging C 1 In response to CCR 10414, "Division 2" has been replaced with "Division 31" in TOPSOIL paragraph Note to conform with CSI MasterFormat.
Aug-2021 N UFGS 32 93 00 Exterior Plants C 1 In response to CCR 10415, "Division 2" has been replaced with "Division 31" in TOPSOIL paragraph Note to conform with CSI MasterFormat.
Aug-2021 N UFGS 32 96 00 Transplanting Exterior Plants C 1 In response to CCR 10416, "Division 2" has been replaced with "Division 31" in TOPSOIL paragraph Note to conform with CSI MasterFormat.
Nov-2021 N UFGS 08 34 16.10 Horizontal Rolling Steel Doors R General periodic update to include new rolling steel door technologies, materials, resiliency, and design methodologies to increase door performance and industry competition. Title changed from STEEL SLIDING HANGAR DOORS.
Nov-2021 N UFGS 08 34 49.00 20 Hemp Shielded Door R Complete review and update including CCR 921.
Nov-2021 N UFGS 26 08 00 Apparatus Inspection and Testing R Complete review and revision including CCRs 7038 and 8614.
Nov-2021 N UFGS 26 11 13.00 20 Primary Unit Substation R Complete review and revision.
Nov-2021 N UFGS 26 11 16 Secondary Unit Substations R Complete review and revision.
Nov-2021 N UFGS 26 13 14 Switchgear House N New section to address the requirements for environmentally controlled, exterior prefabricated, pre-engineered structures to house a coordinated grouping of electrical switchgear and associated power and control equipment.
Nov-2021 N UFGS 26 13 13 Metal-Clad Switchgear N New section to address the requirements for metal-clad switchgear rated 1000 volts and above.
Nov-2021 N UFGS 26 31 00 Facility-Scale Solar Photovoltaic (PV) Systems R Complete review and revision including title change from SOLAR PHOTOVOLTAIC (PV) COMPONENTS.
Nov-2021 N UFGS 27 41 00 Audio-Visual Systems N New section to address the requirements for most audio-visual system projects.
Nov-2021 N UFGS 27 51 23 Intercommunication System N New unified section superseding UFGS-27 21 00.00 20, UFGS-27 21 00.00 40, and UFGS-27 51 23.10 all titled INTERCOMMUNICATION SYSTEM.
Nov-2021 N UFGS 33 01 30.16 TV Inspection of Sewer Lines R Complete review and revision including title change from TV INSPECTION OF SEWER PIPELINES.
Nov-2021 N UFGS 33 01 30.72 Relining Sewers R Complete review and revision.
Nov-2021 N UFGS 35 59 13.16 Extruded and Molded Marine Fenders R Complete review and update. This revision supersedes UFGS-35 59 13.19 ARCH-TYPE RUBBER MARINE FENDERS.
Nov-2021 N UFGS 35 59 13.17 Foam-Filled Marine Fenders N New section developed specifically for foam-filled marine fenders.
Nov-2021 N UFGS 35 59 13.18 Pneumatic and Hydro-Pneumatic Marine Fenders N New section developed specifically for pneumatic and hydro-pneumatic marine fenders.
Nov-2021 N UFGS 01 31 23.13 20 Electronic Construction and Facility Support Contract Management System (eCMS) C 7 In response to CCR 11022, updated requirements for jobsite computer tablet in the Field Administration paragraph, and CCR 11023, updated the Contract Administration paragraph to clarify eCMS file storage structure. Also added minimum download and upload speeds to paragraph 1.4.1 General.
Nov-2021 N UFGS 27 21 00.00 20 Intercommunication System D Superseded by UFGS-27 51 23 INTERCOMMUNICATION SYSTEM. Note: The last published PDF version of this Section is available in the previous release in the UFGS Archives.
Nov-2021 N UFGS 35 59 13.19 Arch-Type Rubber Marine Fenders D Superseded by UFGS-35 59 13.16 MARINE FENDERS. Note: The last published PDF version of this Section is available in the previous release in the UFGS Archives.
Nov-2021 N UFGS 01 35 26 Governmental Safety Requirements C 2 In response to CCR 10735, corrected CFR reference in the Competent Person for Confined Space Entry paragraph and updated the Work Around Flammable Materials paragraph.
Nov-2021 N UFGS 01 58 00 Project Identification C 3 In response to CCR 9882, instructions have been added for Air Force projects on Guam, on both Navy installation with NAVFAC execution and Army installation with USACE execution. Also, clarified Air Force instruction in the first Note in the Project Identification Signboard paragraph.
Nov-2021 N UFGS 03 30 00 Cast-In-Place Concrete C 3 In response to CCR 10400, updated paragraph 2.3.1.2 -Blended Cements, list item c. and 2.3.1.6-Other Supplementary Cementitious Materials. Also updated 3.6.2-Mixing, list item c.
Nov-2021 N UFGS 03 45 00 Precast Architectural Concrete C 2 In response to CCR 9942 (submitted for UFGS-03 45 33), updated the table in the Cementitious Materials paragraph.
Nov-2021 N UFGS 03 45 33 Precast [Prestressed] Structural Concrete C 1 In response to CCR 9942, updated the table in the Cementitious Materials paragraph. Also updated the MATERIALS paragraph.
Nov-2021 N UFGS 08 34 16.20 Vertical Lift Fabric Doors C 1 Targeted update to incorporate recent lessons learned for wire-rope termination, safety arresters, performance standards, warranty and other safety items.
Nov-2021 N UFGS 26 20 00 Interior Distribution System C 3 In response to the following: CCR 10728, "Cable Trays" and optional "Cable Tray Design Data" were added to the Submittal Article under SD-03 and SD-05, respectively, and tagged in the CABLE TRAY paragraph; CCR 10729, optional text added for the cable tray to serve as the EGC in the Trough-Type Cable Trays, Ladder-Type Cable Trays, and Channel-Type Cable Trays paragraphs; and CCR 10730, able Tray Installation paragraph has been updated to prevent partial or complete obstruction of access by cable tray and tray supports.
Nov-2021 N UFGS 26 51 00 Interior Lighting C 2 In response to the following: CCR 10008, changed the LED source replacement requirement from 10% to 15% in the Luminaire Warranty paragraph (list items b and c) and CCR 10327, the integral driver surge protection has been updated to 2 kV in the LED Drivers paragraph, list item f.
Feb-2022 N UFGS 01 58 00 Project Identification C In reference to CCR 11189, Project Sign Details (PDF and zip files) found under Related Materials have been updated. Classified as a clerical change.
Feb-2022 N UFGS 26 05 33 Dockside Power Connection Stations R Complete review; revised to incorporate CCRs.
Feb-2022 N UFGS 41 22 13.55 Bridge Cranes, Under Running, Aircraft Hangar R Complete review and update. Clarified terminology and made changes to submittals along with technical and testing requirements.
Feb-2022 N UFGS 01 14 00 Work Restrictions C 14 In response to CCR 11282, "Naval Base, Norfolk VA" and "Naval Air Station, Norfolk, VA" changed to "Naval Station Norfolk, Norfolk, VA".
Feb-2022 N UFGS 01 35 13 Special Project Procedures C 1 In response to CCR 9539, specifier notes were added to the Definitions and Airfield Obstruction Lights paragraphs; tailoring was corrected to NAVFAC HI for paragraphs 3.2.3 "RIMPAC", 3.2.4 "December 7, 1941", and 3.2.5 "Pearl Harbor"
Feb-2022 N UFGS 01 35 26 Governmental Safety Requirements C 3 Added "Government Designated Authority (GDA)" to Dive Safety Requirements paragraph. In response to CCR 11124, updated first sentence in Competent Person, Cranes and Rigging paragraph.
Feb-2022 N UFGS 08 32 13 Aluminum Sliding Glass Doors C 1 In response to CCR 10477, bracket placement corrected to surround EXTRA STOCK paragraph (1.5)
Feb-2022 N UFGS 08 51 23 Steel Windows C 1 In response to CCR 10430, corrected specifier note for electrical CSI division, provided Army tailoring option for specific submittals within Submittal Article (1.2), and removed brackets from Thermal Performance paragraph (1.5.2)
Feb-2022 N UFGS 08 52 00 Wood Windows C 1 In response to the following CCRs: 10475, 11217, and 11224, submittal item "Engineered Wood Products" has been tailored for NAVY in Submittal Article and corrected submittal tag with in the section text to the proper paragraph Engineered Wood Products (1.2.3). CCRs 10475 and 11225, removed brackets and NAVY tailoring for submittal item "Adhesives" to correct discrepancy since the Adhesives submittal paragraph (2.3.1) is not tailored.
Feb-2022 N UFGS 08 53 00 Plastic Windows C 1 In response to CCR 10476, adjusted location of NAVY tailoring in Material Identification paragraph.
Feb-2022 N UFGS 08 56 46.10 20 Radio Frequency Shielded Enclosures, Demountable Type C 1 In response to CCR 10407, corrected CSI division for Electrical in specifier note for Grounding paragraph (3.8)
Feb-2022 N UFGS 08 56 46.20 20 Radio Frequency Shielded Enclosures, Welded Type C 2 In response to CCR 10408, corrected CSI division for Electrical in specifier note for Grounding paragraph (3.7)
Feb-2022 N UFGS 08 71 00 Door Hardware C 4 In response to the following: CCR 9281, the Hardware Schedule Table (1.5) has been replaced with a hardware item list and a hardware schedule list; CCR 10303, deleted Texture paragraph (2.3.12.3) as it does not apply.
Feb-2022 N UFGS 23 52 33.01 20 Steam Heating Plant Watertube (Shop Assembled) Coal/Oil or Coal C 3 Under Related Requirements, "VAMS 23 09 53.00 20 CONTROLS AND INSTRUMENTATION BOILER PLANT" replaced with "UFC 3-430-11 BOILER PLANT INSTRUMENTATION AND CONTROL SYSTEMS"; also, the term "VAMS" has been removed throughout this section.
Feb-2022 N UFGS 23 52 33.02 20 Steam Heating Plant Watertube (Field Erected) Coal/Oil or Coal C 5 The term "VAMS" has been removed throughout this section.
Feb-2022 N UFGS 23 52 33.03 20 Water-Tube Boilers, Oil/Gas or Oil C 4 The term "VAMS" has been removed throughout this section.
Feb-2022 N UFGS 33 11 00 Water Utility Distribution Piping C 1 Changes made to incorporate multiple CCRs, including updating lead free and PE Pipe requirements and adding PE tubing.
May-2022 N UFGS 01 30 00 Administrative Requirements C 2 Per CCR 9893, updated the Note in paragraph COLOR BOARDS FOR AIR FORCE PROJECTS (1.3) tailored for AIR FORCE to include AFI citation.
May-2022 N UFGS 01 58 00 Project Identification C 4 Per CCR 11078, updated Construction Project Signs paragraph (1.4.3) tailored for ARMY and AIR FORCE to address project identification signs for Air Force projects managed by USACE.
May-2022 N UFGS 02 85 00 Mold Remediation C 1 Per CCR 11701, removed reference to UFGS 00 22 13.00 20 in first Editor’s Note of Description of Work paragraph (1.3.1)
May-2022 N UFGS 26 13 00 SF6/High-Firepoint Fluids Insulated Pad-Mounted Switchgear C 1 Per CCR 8883, updated Automatic Switch Controls paragraph (2.1.4) with options for 120Vac control power.
May-2022 N UFGS 31 62 13.13 Cast-In-Place Concrete Piles C 2 Per CCR 11703, removed reference to UFGS 00 22 13.00 20 in Measurement and Payment paragraph (1.2.2)
May-2022 N UFGS 31 62 13.20 Precast/Prestressed Concrete Piles C 1 Per CCR 11704, removed reference to UFGS 00 22 13.00 20 in UNIT PRICE paragraph (1.6)
May-2022 N UFGS 31 62 13.24 Concrete Cylinder Piles C 1 Per CCR 11705, removed reference to UFGS 00 22 13.00 20 in UNIT PRICE paragraph (1.6)
May-2022 N UFGS 31 62 13.26 Pressure-Injected Footings C 1 Per CCR 11707, removed reference to UFGS 00 22 13.00 20 in Unit Price paragraph (1.4.3)
May-2022 N UFGS 31 62 16.13 Steel Pipe Piles C 1 Removed reference to UFGS 00 22 13.00 20 in Unit Price paragraph (1.4.4)
May-2022 N UFGS 31 62 16.16 Steel H-Piles C 1 Per CCR 11708, removed reference to UFGS 00 22 13.00 20 in Unit Price paragraph (1.4.3)
May-2022 N UFGS 31 62 19 Timber Piles C 1 Per CCR 11709, removed reference to UFGS 00 22 13.00 20 in Unit Price paragraph (1.4.3)
May-2022 N UFGS 31 62 19.13 Timber Marine Piles C 2 Per CCR 11710, removed reference to UFGS 00 22 13.00 20 in BASIS OF BIDS paragraph (1.5)
May-2022 N UFGS 31 62 50 Densified Aggregate Piers C 1 Per CCR 11712, removed reference to UFGS 00 22 13.00 20 in Unit Price paragraph (1.4.3)
May-2022 N UFGS 31 63 26.60 [Grouted] Helical Piles C 1 Per CCR 11716, removed reference to UFGS 00 22 13.00 20 in Unit Price paragraph (1.4.3)
May-2022 N UFGS 41 22 13.55 Bridge Cranes, Under Running, Aircraft Hangar C 1 Added technical requirement to second text paragraph in subpart 2.3.2.2 Load Block and Hook
May-2022 N UFGS 00 22 13.00 20 Supplementary Instructions to Offerors D This Section has been removed from the UFGS data set and superseded by a Word document (for NAVFAC use). The new Price Schedule can be accessed here. Note: The last published PDF version of this Section is available in the previous release in the UFGS Archives.
May-2022 N UFGS 05 05 20 Post-Installed Concrete and Masonry Anchors N Unified / Section Number Change: Superseding 05 05 20.00 27 without Revision
May-2022 N UFGS 05 05 20.00 27 Post-Installed Concrete and Masonry Anchors D Section Number Change: Superseded by UFGS-05 05 20 without Revision. Note: The last published PDF version of this Section is available in the previous release in the UFGS Archives.
May-2022 N UFGS 09 97 13.17 Three Coat Epoxy Interior Coating of Welded Steel Petroleum Fuel Tanks R Complete review and update.
May-2022 N UFGS 09 97 13.27 High Performance Coating for Steel Structures R 08/25/2022: this version has been made inactive and replaced with the previous Feb 2021 version. Complete review and update.
Aug-2022 N UFGS 01 57 19 Temporary Environmental Controls R Revised to align with current industry standards and DoD requirements. This Section supersedes UFGS-01 57 19.00 20 Supplemental Temporary Environmental Controls as all requirements are contained within this Tri-Service, tailorable specification as reorganized paragraphs in a hierarchical presentation.
Aug-2022 N UFGS 01 57 19.01 20 Supplemental Temporary Environmental Controls D Superseded by UFGS 01 5719 Temporary Environmental Controls Note: The last published PDF version of this Section is available in the previous release in the UFGS Archives.
Aug-2022 N UFGS 31 31 16.13 Chemical Termite Control R Complete review and update.
Aug-2022 N UFGS 31 31 16.19 Termite Control Barriers R Complete review and update.
Aug-2022 N UFGS 33 52 80 Liquid Fuels Pipeline Coating Systems R Complete review and update.
Aug-2022 N UFGS 01 58 00 Project Identification C 5 In response to CCR 11903, corrected placement of tailoring tags and updated specifier notes throughout.
Aug-2022 N UFGS 03 30 00 Cast-In-Place Concrete C 4 In response to the following CCRs: 10852, deleted paragraph Maximum Allowable Construction Joint Spacing (3.11.1) and list items a. and b.; 11572, updated Concrete Mix Design paragraph (1.6.1.2); 11445, updated Table under Sulfate Resistance paragraph (2.5.2.4 list item a.); 11120, removed list item b. under Reinforcement paragraph (6.2) and added list item e. under Epoxy-Coated Reinforcing Bars paragraph (2.6.1.2); and 11115, added ASTM A1094/A1094M to the Reference Article and as an option in paragraph Galvanized Reinforcing Bars (2.6.1.1) list item a.
Aug-2022 N UFGS 46 07 53 Packaged Wastewater Treatment Equipment C 1 In response to CCR 11920, NASA tailoring was added to the Electrical Work paragraph (3.2.2)
Aug-2022 N UFGS 09 97 13.27 High Performance Coating for Steel Structures C 1 The May 2022 version of this Section has been made inactivate as it conflicted with FAR requirements; the February 2021 version has been reinstated with changes made to TEST KITS (subparts 2.6.1 and 2.6.2)
Nov-2022 N UFGS 01 14 00 Work Restrictions R Complete review to reset section date; address CCRs 12149 & 12150, added "U.S. persons" to General Construction and Finish Work note and paragraph.
Nov-2022 N UFGS 02 84 16 Handling of Lighting Ballasts and Lamps Containing PCBs and Mercury R Complete review to correct passive voice and address CCRs.
Nov-2022 N UFGS 02 84 33 Removal and Disposal of Polychlorinated Biphenyls (PCBs) R Complete review to correct passive voice and address CCRs.
Nov-2022 N UFGS 08 34 49.00 20 Hemp Shielded Door R Complete review to correct passive voice and address CCRs.
Nov-2022 N UFGS 08 71 63.10 Electrical Locking Control for Brigs R Complete review to correct passive voice and address CCRs.
Nov-2022 N UFGS 26 08 00 Apparatus Inspection and Testing R Complete review to correct passive voice and address CCRs.
Nov-2022 N UFGS 26 12 21 Single-Phase Pad-Mounted Transformers R Updated section to address CCRs
Nov-2022 N UFGS 41 22 13.15 Bridge Cranes, Overhead Electric, Under Running Trolley R Complete review and major update, including title change (from BRIDGE CRANES, OVERHEAD ELECTRIC, UNDER RUNNING). Clarified terminology and made changes to submittals along with changes to technical and testing requirements.
Nov-2022 N UFGS 23 64 26 Chilled, Chilled-Hot, and Condenser Water Piping Systems C 6 Updated paragraph "Valves" (3.1.5) removed sentence regarding omitting isolation valves
Nov-2022 N UFGS 33 56 21.17 Single Wall Aboveground Fixed Roof Steel POL Storage Tank C 2 In response to various CCRs, including #11869, added ASME BPVC IX to "References" and "Welding Qualifications" paragraph (1.6.1); #11875 added API Std 650 to "Shell Height" paragraph (1.5.1.2), #11983 updated "Roof Perimeter Guardrail" paragraph (2.13.10) and added new Designer Note; #6124 removed wiper requirement and added non-corrosive materials for tape drum and cassette to "Mechanical Tape Level Gauge" (2.13.5) and (2.13.6) paragraphs; and #11261, revised opening Note to coordinate use of floating pans with UFC 3-460-01.
Nov-2022 N UFGS 41 22 13.55 Bridge Cranes, Under Running, Aircraft Hangar C 2 Updated formatting with some changes to technical requirements.
Feb-2023 N UFGS 01 14 00 Work Restrictions C 1 In response to CCR 12429, updated work requirements at Naval Base Kitsap.
Feb-2023 N UFGS 01 20 00 Price and Payment Procedures C 3 In response to CCR 12177, replaced "lump sum" with "Job" in second Note for Army projects, removed "lump sum" from DREDGING paragraph (1.11).
Feb-2023 N UFGS 01 31 23.13 20 Electronic Construction and Facility Support Contract Management System (eCMS) C 8 In response to CCR 12594, updated ECMS UTILIZATION paragraph (1.6) to clarify when contractors must utilize eCMS for transferring submittals.
Feb-2023 N UFGS 07 27 36 Spray Foam Air Barriers C 3 In response to CCR 12503, updated SUBMITTALS article and Prohibited Materials paragraph (2.1.5) to disallow all HFC blowing agents.
Feb-2023 N UFGS 07 57 13 Sprayed Polyurethane Foam (SPF) Roofing C 4 In response to CCR 12504, updated SUBMITTALS article and SPRAY URETHANE FOAM paragraph (2.2) to disallow all HFC blowing agents.
Feb-2023 N UFGS 41 22 13.15 Bridge Cranes, Overhead Electric, Under Running Trolley C 1 Added an option for alternate wire rope in Division 2 hazardous areas. Updated formatting, references, foreign standard practices, and provided clarifications.
Feb-2023 N UFGS 41 22 13.55 Bridge Cranes, Under Running, Aircraft Hangar C 3 Added an option for alternate wire rope in Division 2 hazardous areas. Updated formatting, foreign standard practices, and provided clarifications.
Feb-2023 N UFGS 12 00 01.00 20 Furniture, Fixtures and Equipment (FF&E) Package N New section developed for the design, procurement and installation of furniture, fixtures and equipment (FF&E) for new construction and building renovation projects.

Pages