AFH 10-222, VOLUME 5 Guide to Contingency Electrical Power System Installation, with Change 1  

Date: 
07-01-2008

This handbook addresses actions necessary to install contingency electrical generation and distribution systems equipment found in the Basic Expeditionary Airfield Resources (BEAR) equipment sets, including legacy systems that may have been transitioned into the BEAR program to support austere base force deployments.

This handbook applies to Electrical Systems and Electrical Power Production technicians charged with providing power generation and electrical distribution systems support for contingency beddowns, including Air National Guard (ANG) units and Air Force Reserve Command (AFRC). Readiness and deployment planners and base level mobility team chiefs responsible for contingency planning should also use it for information regarding siting issues and requirements. This guide may also be used in support of peacetime contingencies.

Page(s): 
143
Federal Facility Criteria: 
Topics: